Important Note:
This information is provided as a basic guide of
recommended techniques for the installation of the Hambro® Composite Floor System. It is not intended to take the place
of the requirements of applicable building codes. All work
must be in accordance with the Contract Documents and “Field-Use”
Hambro® Shop Drawings for the specific project. Accordingly,
while these guidelines are intended as recommended general
techniques to be followed, these techniques can be used only
to the extent they do not conflict with building code requirements,
construction documents and site conditions. You are requested
to contact Swirnow Structures LLC for conditions not clearly
covered in this guide.
Shop Drawings are provided by Swirnow Structures
LLC for review and approval by Purchaser, the Architect, and
Engineer of Record to verify and coordinate the joist locations,
spans, capacities, loads, details, and to check for correctness
in relation to project plans and specifications. Shop Drawings
are based on the latest information provided to the Supplier
which may differ from the contract documents. Hambro® Joists are fabricated only in accordance with the “Field-Use”
Hambro® Shop Drawings. Shop Drawings must always be used in
conjunction with the construction documents.
1. TOOLS
- Large hammer and 2" x 4" for tapping joist
shoes for proper bearing, and the forms under the joist
seats and beam flanges, if applicable.
- Circular saw, crowbar, hammers.
- Minimum two 2' x 6' long rolling scaffolds for Rollbar® installation.
- (2) 4' pipes for levering tight Rollbars® in and
out.
- Pallet jack, for large floor areas for movement of pallets
of Rollbars® and plywood.
- Form oil and applicator, optional. (Do not spray the
joists or mesh.)
Back to Top
2. UNLOADING STORING AND HANDLING
Delivery: Hambro® joists will arrive in full tractor-trailer
loads banded in nested bundles. Suitable access must be provided
so that trucks can move under their own power. Proper equipment
must be provided to unload the joists and Rollbars®.
Joist Identification: Hambro® joists are tagged with
an identification plate attached at one end on the joist shoe.
(Tag End)
Upon delivery, all materials must be crosschecked with the
packing list by the buyer and/or erector at the jobsite. All
discrepancies and damages must be promptly reported to seller
within 48 hours of delivery, otherwise replacement joists
will be an additional charge
Storing: The Hambro joists must be stored upright on
a flat surface, and joists should be stacked carefully to
prevent damage. Care shall be exercised at all times to avoid
damage through careless handling during unloading, storing,
and erecting. Time will be saved during the erection process
if, while unloading the bundles, they are stacked in some
organized fashion, either by mark or floor with tags all facing
the same direction.
Hoisting: When hoisted by crane, the cables can be placed
at each end or at third points of the joists. Cables must
be placed under the top chord and never attached to the web
members.
Damaged joists, regardless of the reason, may impair the
performance and safety of the system and must be repaired
or replaced prior to erection. DO NOT MAKE FIELD REPAIRS TO
DAMAGED Hambro JOISTS WITHOUT WRITTEN APPROVAL FROM YOUR
STRUCTURAL ENGINEER AND CONSULTING WITH A QUALIFIED HAMBRO ® REPRESENTATIVE.
Back to Top
3. SETTING THE JOISTS
Typical Spacing: Hambro® joists are typically spaced
4'-1¼" on center (o.c.), but to start the erection
procedure, space them at approximately 4' o.c. on the bearing
provided.
Five points where extra care should be taken:
- Direction of Top Chord: It is an absolute necessity that
all top chords face the SAME DIRECTION within a bay. This
is confirmed by joist tag end directions shown on the Shop
Drawings. The tag end of the joist will have a small stamped
steel tag with the joist mark on it.
As you will note from Diagram #1, forms butt on one side
of the top chord, but tuck under on the opposite side. If
the joists are not installed as indicated, forms will not
fit properly i.e. the forms will be too wide or too narrow
to suit the joist spacing.

- Special joists (i.e. deep shoes, point loads or HangerplateTM)
will determine the direction of the tag end. The direction
of the tag ends are shown on the shop drawing. Before you
start the installation, determine the proper direction of
the tag ends from the shop drawings.
- End Joists: A close measurement should be taken for the
first joist that is set, usually the one next to the wall,
beam, or tie joist. Careful measurement of this spacing
will save unnecessary excessive shifting of the system after
all of the joists are set and Rollbars® are in place.
All measurements should be taken from the slots of joist
top chords
- Bearing: It is important to make sure that the joist
shoes are placed properly on the supporting walls or beams.
Joists should be centered between walls or beams so that
you get equal bearing for both shoes. Follow the minimum
dimensions specified on the “Field-Use” Hambro® Shop Drawing. Unless noted otherwise, the minimum bearing
on masonry and wood support is 3½”, and 2½”
on structural steel. REDUCED BEARING COULD PRESENT A SAFETY
HAZARD. As soon as the Hambro? joist is installed the Rollbar® shall be installed.
- Long Joists: Pay particular attention to the erection
of long Hambro® joists. Joists shall be adequately braced
using Rollbars® immediately after setting to prevent
lateral movement. The joist must be straight (no sweep)
and plumb before placing the concrete.
Important: As soon as the joists are erected, the remaining
Rollbars® should be installed.
Welding joist shoes may sometimes be required when bearing on a steel frame or steel studs, to restrain the frame as required by the Engineer of Record.
Back to Top
4. INSTALLING THE ROLLBARS®
Slots in the top chord are 5/8" x 1¾" and
spaced 7" o.c. The first Rollbars® at the end of
the joist, nearest the beam or wall, must be installed with
the clip angles on the Rollbars® facing the wall or beam.
They can only be removed by rotating the handles away from
the wall and the clip angles pivoting away from the bottom
of the plywood form.
ROLLBARS®: Note the various types and their specific
purpose. Rollbars® are delivered F.O.B. the jobsite, by
Supplier, for your use. The Purchaser must have suitable equipment
on site to both load and unload the Rollbars® on and off the
Supplier’s truck.
| Standard Rollbar® (SRB) is used for typical 4’-1¼”
joist to joist, joist to FlangehangerTM spacing. Also available
in 5’-0” and 5’-¼” lengths. |
 |
| Extension Rollbar® (ERB) is adjustable
for joist to joist, and joist to FlangehangerTM spacing.
Small ERB from 1’-10¾” to 3’-1”.
Large ERB from 3’-1” to 4’-7”. |
 |
| Telescopic Rollbar® (TRB) has a short tail on one
end and a flat arrow tip on the other end for joist to
ledger spaces only. 2’-8” to 4’-7”.
|
 |
FlangehangerTM is a 13-gauge angle shipped in 20' lengths.
FlangehangerTM is an optional accessory that is provided only
when specifically ordered. The FlangehangerTM has slots in
the vertical leg which correspond to the slots in the Hambro® joist top chord. FlangehangerTM is field cut to length for
attachment to steel beams which are parallel to the joists.
It can be welded or power shot to the flange of parallel beams.
Once the FlangehangerTM has been securely attached, the Rollbars® can be supported by the beams. NOTE: FlangehangerTM is attached
ONLY TO BEAMS WHICH ARE PARALLEL to the Hambro® Joists
and remains permanently attached to the beam.

Spacing: The Hambro® joist top chord has pre-punched holes every 7". In order to support forms properly, care should be taken to install the Rollbars® at 21" o.c. (every third hole), for the usual 2¾" to 3½" slab. Exceeding this dimension would be dangerous, since it overloads the Rollbars® and plywood. IMPROPER SPACING OF ROLLBARS® MAY AFFECT THE STRUCTURAL SAFETY OF THE SYSTEM DURING THE CONCRETING STAGE. There should be a Rollbar® 7" from the end of each plywood form.
Thickened Slabs: In the areas where thicker slabs are specified, Rollbars® should be placed at closer intervals. Where certain areas have been thickened or HangerplateTM is used, Rollbars® should not be spaced more than 14" o.c. for slabs 3¾" to 6" thick and 7" o.c. for slabs exceeding 6" thickness.
Stagger Rollbar® spacing from bay to bay whenever possible
to avoid having two Rollbar® ends in the same slot. This
will simplify the stripping procedure. This does not apply
to the temporary bottom chord bracing or the first Rollbar® nearest the supporting beam or wall.
Sequence of Installation: Standard Rollbars® should be
installed first, starting with the ends of the first two joists
in the bay, and working toward the middle of the bay. Install
the Telescopic Rollbars® last.
Temporary Bottom Chord Bracing: To provide additional stability
during concreting, Rollbars® shall be inserted in the
clips that are welded to the bottom chords of the joists.
This temporary bracing is removed when stripping the forms,
as it is not required at the composite stage. At the end of
each joist run, bottom chord bracing must be firmly braced
to stable walls, or beams or main structural frame and be
firmly attached at both ends. In the absence of stable walls
or beams, “X” bracing must be used. (See Diagram
#4.) “See plans for location of temporary bottom chord
bracing.

CAUTION:
To prevent lateral movement of the top chords during construction,
the lateral support provided by regular 4'-1¼"
slotted Rollbars® must be carried on right through to
the end walls or beams. Where TRB's have been used between
joists (odd spacing), positive spreaders must be spaced at
¼ points (i.e., a 2" x 4" cut to exact length).
Note: Plywood forms ripped to the exact width will help provide
the required lateral support.
NOTE: Bracing must be continuous at bottom chords during
construction to ensure that all joists remain vertical. At
end joists, where no wall or structural frame is present,
brace bottom chord to the floor or grade.
NOTE: For smaller than "standard bays" but greater
than 2'-8" (Diagram #5), you should use the Telescopic
Rollbars® supplied to support the forms. Caution: Telescopic
Rollbars® should never be placed on top of a wall or beam
as the form will be at the wrong elevation and encroach into
the slab thickness in that area. Telescopic Rollbars® should always be placed on ledger strips. On steel frame projects,
FlangehangerTM placed on top of the beam flange proves to be
a time saver. Only Extension and Standard Rollbars® can
be used with FlangehangerTM. Note: for joist spacing up to
1’ 9¾" and less (Diagram #6), #4 rebar should
be used to support the forms (supplied by installer).

IMPORTANT NOTICE: The Rollbars® shipped to the site
are either new or used. During the course of the project,
the Rollbars® may be bent. All workmen should be informed
of the importance of a proper and improper bow in the Rollbars®.
A Rollbar® which has rotated out of plumb has virtually
no capacity to support the construction loads and is an unsafe
condition.
Back to Top
5. PLACING THE REMOVABLE PLYWOOD
FORMS
Plywood Type: The standard spacing (4'-1¼") is
designed to accept a standard 4' x 8' sheet of CDX 3/8"
or ½" plywood. When using a 3/8" sheet of
plywood, the forms are to be overlapped at least 12".
When using ½" plywood, all joints should be butted
since the thickness would encroach into the area of the top
chord that is designed to be imbedded into the concrete. When
the choice is available, you will find it more economical
to use 3/8" plywood and "lap the joints".
End Bay Condition: When placing the plywood forms next to
the end joist, be sure to avoid having the plywood sit on
the bearing wall or beam. You will find that a plywood form
bonded between the concrete pour and the bearing wall or beam,
is no longer removable and has to be chopped out.
NOTE: In order to take advantage of the system’s flexibility,
it is recommended that the builder and other subcontractors
check the position of the joists in relation to any risers
and slab openings, etc., which will be coming through the
deck prior to placing the forms in the end bays. At this point,
before end bays are formed, in most cases, the entire deck
can be shifted a few inches in either direction. Check and
adjust joist spacing if necessary.
Oiling plywood is not required, however, it will save labor
in stripping and will prolong the useful life if the forms.
Forms are ordinarily stripped the day following the pour,
provided the concrete strength has reached 500 psi. DO NOT
OIL THE JOISTS OR MESH.
Slab Penetrations are achieved by attaching the desired size
sleeve directly to the plywood. Foam blocks or short lengths
of pipe are commonly used. After the slab is poured, the forms
are removed with the plywood. Openings greater than 8"x
8" require double mesh and possibly rebar. Avoid placing
openings closer than 6" to the joist top chord so as
not to interfere with the composite action. Refer to structural
drawings for reinforcement at openings and clear distance
to joists.
CAUTION:
- Bundles of plywood, mesh or Rollbars® should be placed
on supporting walls or beams, never on the joist system.
The system is not designed for this condition and will present
a serious safety hazard, along with damage to the joists.
Break down all bundles to ensure load distribution in accordance
with design loads at all times.
- Before any load is imposed on joists and prior to the
plywood forms being installed, there should be at least
four joists bays completed with standard Rollbars® including
the temporary bottom chord bracing installed to safely develop
the structural non-composite capacity of the Hambro® joists.
- Full sheets of plywood are recommended. When shorter
pieces are used, make sure they are adequately lapped and
supported and safe for workers and construction loads.
Back to Top
6. PLACING THE MESH
Flat sheets of welded wire mesh are recommended in lieu of
rolled mesh for its ease of handling, and because it lays
more naturally without the ends sticking up. The flat sheets
are laid across the joists with the long dimension running
from joist to joist.
Lapping: Be sure to get the minimum lap of 6" perpendicular
to joists and 12" lap parallel to joists. Be sure the
mesh extends onto the perimeter beams or walls at least 4"
in order to develop the capacity of the slab.
Unless otherwise noted on the “Field-Use” Hambro® Shop Drawings, a single layer of mesh is all that is typically
required. On the Hambro® Shop Drawings, a hatched area
indicates two layers of mesh.
Always check the final construction documents or approved
erection drawing for the proper reinforcement and mesh type
and follow the construction drawings for the placement of
slab reinforcement.
The flat sheets of mesh should drape naturally. Do not step
down the mesh on either side of the top chord.
Back to Top
7. PLACING THE CONCRETE
Concrete Note: When estimating the concrete volume, assume
a coverage of approximately 99sf per cubic yard for a 2¾”
slab. This takes into account the minor variation in slab
thickness due to the lapping of the formwork and a nominal
amount of waste. Additional material should be added for thickened
areas, cantilevered slabs or special conditions as required.
Swirnow Structures is not responsible for variations in material
or labor costs.
Concrete Mix: The minimum concrete compressive strength is
3,000 psi. The aggregate in the concrete mix should not be
greater than ¾".
Screeding: When screeding, maintain a minimum depth of 1¼"
above the top chord for a nominal 2¾" slab. You
will notice that the joists are fabricated with a positive
camber to offset the deflection caused by the weight of the
concrete. It will come out as the slab is poured, leaving
a small residual camber for the remaining design load.
Slump: Field experience has shown that a 3½" to 4½" slump is easy to work with and finish. Greater slumps will create excessive leakage and costly clean up. Refer to the Structural Drawings and Project Specifications for requirements.
CAUTION: Too high a slump reduces the strength of the concrete
and causes excessive shrinkage cracks. Curing procedures should
be in accordance with the latest ACI requirements.
Vibrating: The concrete is to be lightly but thoroughly vibrated
to ensure:
- The full encasement of the top chord in the concrete
(letting the vibrator hit the top chord will assure encasement).
This is very important to obtain the full design capacity
of the system.
- Elimination of "honeycombs".
- The concrete is vibrated under the mesh to achieve proper
concrete cover.
Construction Joints: When pouring and finishing a deck, it
is not necessary to complete the entire deck monolithically.
If it becomes necessary to stop the pour parallel to the joists,
the joint should be midway between the joists, but never closer
than 6" to the top chord. The mesh must extend at least
12" beyond the break. If you stop a pour perpendicular
to the joists, locate the joint over the supporting walls
or beam.
SAFETY PRECAUTIONS WHEN POURING CONCRETE:
Several simple precautions must be followed before and during
the concrete pour to ensure a safe operation:
- Assign a man below during the pour to check that all
Rollbars® remain in proper position during the pour.
Prevent others from working under the deck when pouring
concrete.
- As previously mentioned, Rollbar® spacing should
be reduced if slabs thicker than 3½ " are to
be poured, or joist spacing exceeds 4'-1¼".
- Check that plywood forms are properly lapped or butted,
and that they have not moved sideways into the top chord.
- During the pour, care should be taken not to subject
the joists to excessive construction loads or the performance
and safety of the system may be impaired. Do not pour concrete
in excess of slab thickness specified on drawings, and do
not drop large bucket loads or pump excessive concrete in
a concentrated area.
- The pre-punched holes in the top chord section and the
Rollbars® are not designed to support buggies; therefore,
runways must be placed across the top chord. This is usually
accomplished with wood planks, laid perpendicular to the
joists.
- CAUTION: Do not overload the slab or joists at any phase
of construction.
Back to Top
8. STRIPPING THE FORMS
At such time as the concrete reaches a cylinder strength
of 500 psi, the Rollbars® and plywood forms can be stripped.
The concrete deck is ready for work when the cylinder strength
reaches 1,000 psi.
Avoid dropping Rollbars® on slab, as this may cause chipping
of the concrete surface. Avoid dropping the plywood forms
when stripping. This causes damage to corners and edges and
reduces the amount of re-use.
After stripping, Rollbars® should be neatly stacked parallel
to each other on a pallet before transporting.
- Care should be exercised not to overload the system;
pallets of block and bundles of mesh, plywood or gypboard
should be placed over supporting walls or beams or spread
out when placed on the slab.
- DO NOT MODIFY OR ALTER ANY Hambro PRODUCT WITHOUT
FIRST OBTAINING WRITTEN APPROVAL FOR THE DESIRED CHANGE
FROM THE STRUCTURAL ENGINEER, AND GUIDANCE FROM A QUALIFIED
HAMBRO® REPRESENTATIVE.
- Similarly, if it becomes necessary to deviate from the
“Field-Use” Hambro® Shop Drawings supplied
with each job, obtain approval of the structural engineer
prior to making that change.
- When core drilling a slab, avoid drilling within 6"
of a joist. Openings 8" x 8" or larger require
double mesh and possibly rebar. Consult the structural engineer.
Refer to structural drawings for reinforcement at openings
and clear distance to joists.
- In the event a joist is damaged, by whatever cause, obtain
written approval from the project structural engineer before
it is used. Replace joists as directed by the Engineer of
Record.
- In hot, sunny weather, to precaution to wet down the
deck with water to prevent the concrete from setting too
rapidly, which may cause excessive shrinkage cracks to appear.
Always follow ACI requirements.
Back to Top
9. CORRECTIVE REMEDIES IN
THE FIELD
There are certain conditions that, in some instances, appear
and are not to be considered "manufacturing defects".
Because of Hambro's® simplicity, they are corrected in
the field as a standard procedure by the installer. All corrective
measures shall be subject to the Engineer of Record’s
approval prior to implementation.
- Joist Sweep: Occasionally, some Hambro® joists may
exhibit excessive sweep. This condition is easily corrected
as a standard procedure of the installer at the job site.
In the few instances where necessary, simply lay the joist
on its side, supported at each end. The weight of one or
two workmen standing on the joist will usually correct this
sweep. Minimal sweep is nothing to be concerned with, as
long as there are relatively straight joists at the beginning
of the installation. The continued application of Rollbars® will then further straighten successive joists that may
have minimal sweep. No concrete shall be poured on any decks
where joist sweep exceeds manufacturer’s tolerances.
- Bent Shoes: Bent shoes which are no longer 90o to the
plane of the web are corrected by simply hammering them
level or by merely shimming the out-of-level areas so as
to plumb the joist and obtain adequate bearing. The grout
in the concrete mix will readily run under the shimmed shoes.
Shimming should be done using metal.
Hambro® Gives You Every Advantage
- OPEN WEB JOIST CONFIGURATION, NO BRIDGING, AND 4’
JOIST SPACING accommodates mechanical distribution within
the joist plenum; permits full lengths of duct and water
pipe, reducing the many connections when using shorter lengths.
Virtually eliminates dropped and soffit enclosures.
- REDUCES BUILDING HEIGHT and develops savings in the cost
of skins and all other vertical components.
- SHALLOWER JOISTS WITH RIGIDITY AND STIFFNESS; Hambro® composite design generally saves 2 to 4 inches against conventional
joist systems. Hambro® slabs key into voids in block
and encase top flange of interior beams, develops diaphragm
action and ties the structure together.
- VERY WELL SUITED FOR WOOD, STEEL STUD, STEEL, AND CONCRETE
FRAMES.
- U.L. DESIGNS FOR 1, 2 AND 3 HOURS
with gypsum board, spray fire-proofing or acoustical tile.
One layer of fire code gypsum screw-attached to furring channels spaced 2' o.c. provides up to 3 hours of protection. For up to 1 ½” hours, U.L. Designs permit unprotected ceiling penetrations of up to 196 sq.
in. per 100 sq. ft. of ceiling area (2 hours permits 100 sq. in.)…eliminating fire
dampers or protection at ceiling openings.
- STC 57 ON BARE CONCRETE.
- SLAB PENETRATIONS ARE EASY using either sleeves, styrofoam or wood blocking prior to concreting. No metal decking to cut or tendons to be concerned with. Fewer joists offer flexibility. Slender 3,000 psi slab makes coring simpler, if necessary.
Approvals
The Hambro® Composite Floor System has been approved,
listed, classified, recognized, certified, and/or accepted
by the following leading national and local building codes
and authorities:
- Building Officials Code Administrators (B.O.C.A.)
- Underwriters Laboratories, Inc. designs for 1, 2, and
3 hour fire ratings
- Southern Building Code Congress International (S.B.C.C.I.)
- International Conference of Building Officials (I.C.B.O.)
- Housing & Urban Development-Federal Housing Administration
(HUD-FHA)
- Metropolitan Dade County Building Code
- New York City; Philadelphia; Baltimore; Washington, DC;
Fairfax County; etc.
- U.S., Canada and Foreign patents around the world
Back to Top
Download the Installation Guide in Adobe Acrobat Reader PDF format.

|